Field Notes...

First Build of a Full Home Structure Completed in Under Three Days
Hadrian X® Factory Acceptance Testing completed

FBR successfully demonstrated its robotic home building technology by building a 180m2, 3-bedroom, 2-bathroom home structure in less than the targeted total elapsed time of three days, a technical milestone that was set for the Company in 2015.

This represented a world first achievement for the Company and the most significant technical milestone completed in the Hadrian X® programme at the time. It followed the successful completion of Factory Acceptance Testing of the Hadrian X® construction robot.

View more projects

TECHNICAL SPECS

Type: Residential
Layout: 3 Bedroom, 2 Bathroom Demo Structure 
Wall Area: 180sqm
Wall Length: 75m
Total Distance Travelled by Lay Head: 1138m
Block Type: FBR-designed F Block (External and Internal)
Block Size: 490mm x 230mm x 240mm & 490mm x 230mm x 115mm
Blocks Laid: 1,314 Blocks (Approx. 12,200 SBEs)
Wall Type: Double Leaf Cavity Wall
Time to Completion: 3 Days
Status: Complete

FBR Technology